Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
SOUTHBRIDGE- BRIDGE DEMOLITION & ROAD RELOCATION, S-21-014, SR 169 (NORTH WOODSTOCK ROAD) OVER THE P&W RAILROAD (ABANDONED)
The purpose of this project is to improve the roadway and traffic conditions of North Woodstock Road by removing the existing bridge, approaches, and highway embankments, and lowering the roadway to its original grade before the bridge had been constructed. This will involve complete reconstruction of North Woodstock Road from where it intersects East Main Street to just south of the intersection between North Woodstock Road and Golf Street. The roadway reconstruction will include the excavation of North Woodstock Road to allow for a straighter alignment.
Location:
  • Town of Southbridge
  • Resident Engineer: Stanley Choinski
    Construction Contract Value: $1,869,983.50
    Construction Bid Price: $1,471,001.00
    Initial Construction Estimate: $2,701,237.20
    District: District 3

    Contracts (2) Progress
    # 64308 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 72423 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Bridge Demolition) North Woodstock Road (Route 169) over the Abandoned CSX Railroad Line. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/01/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/02/2008
    Project Initiation Form PIF Entered 02/03/2009
    Project Initiation Form PRC Submitted 02/03/2009
    Project Review Committee PRC Approved 02/12/2009
    Project Review Committee Letter 02/27/2009
    Project Status Advertised 01/14/2012
    Project Management
    25% Design 25% Package Received 01/11/2011
    25% Design 25% Package Approved 02/10/2011
    25% Design Design Public Hearing 04/28/2011
    75% Design 75% Package Received 06/20/2011
    75% Design 75% Package Comments to DE 08/01/2011
    75% Design 75% Plans Approved 08/01/2011
    Final Design PS&E Received 08/30/2011
    Final Design PS&E to FAPRO 01/11/2012
    Consultant Contract Process NTP Issued 07/17/2009