Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
SPRINGFIELD- BRIDGE REPLACEMENT, S-24-028, ST. JAMES AVENUE OVER CONRAIL RAILROAD (ABANDONED)
Location:
  • City of Springfield
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Construction Begins: Spring 2027
    Project Manager: Jonathan E Freeman
    Estimated Total Contract Cost: $9,146,500.00
    Estimated Total Federal Participating Construction Cost: $9,609,490.00
    Funding Provision: This project is planned to be funded through the 2027 Transportation Improvement Program for the Pioneer Valley Metropolitan Planning Organization.
    District: District 2
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    Planned Federal FY: 2027
    Responsible MPO: Pioneer Valley Metropolitan Planning Organization
    Location: Municipality
    Cities: SPRINGFIELD
    Category: Advertised Projects Constr.
    Budget Section: 3B
    Advance Construct: No
    Air Quality Exempt: No

    No comments for this TIP line
    Category FA - Next Generation Bridge GANs
    Federal Cost: $4,343,412.80
    State Cost: $1,085,853.20
    Total Cost: $5,429,266.00

    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/02/2008
    Project Initiation Form PIF Entered 10/12/2011
    Project Initiation Form PRC Submitted 04/14/2021
    Project Review Committee PRC Approved 05/31/2024
    Project Management