Project Description:
SWANSEA- SUPERSTRUCTURE REPLACEMENT, S-35-018, I-195 (EB/WB) OVER THE COLE RIVER
The project involves both I-195 eastbound and westbound bridges over Cole River in Swansea. The work shall consist of the construction of new superstructures adjacent to the existing bridges on temporary bents and sliding them transversely into their final location. The new superstructures shall be built on temporary bents which shall extend under the existing bridge superstructure. The new superstructures will feature a span length of approximately 125 feet and shall consist of steel plate girders with a composite concrete deck.
Location:
  • Town of Swansea
  • Resident Engineer: Rajat Gogoi
    Construction Contract Value: $12,622,546.00
    Construction Bid Price: $10,501,275.05
    Initial Construction Estimate: $11,607,616.25
    District: District 5

    Contracts (4) Progress
    # 54836 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 57467 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 60139 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support servives to support the Bridge Preservation/Betterment Program. Final
    # 79399 -- Construction Contract
    2 Superstructure Replacement (S-35-018) (Steel) - Interstate 195 (EB and WB) over the Cole River. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/27/2014
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/02/2008
    Project Initiation Form PIF Entered 02/03/2009
    Project Initiation Form PRC Submitted 02/03/2009
    Project Review Committee PRC Approved 02/12/2009
    Project Status Advertised 08/24/2013
    Project Management
    25% Design 25% Package Received 04/20/2012
    25% Design 25% Package Comments to DE 05/02/2012
    25% Design Design Public Hearing 02/12/2013
    25% Design 25% Plans Complete 06/25/2012
    75% Design 75% Package Received 03/21/2013
    75% Design 75% Package Comments to DE 06/06/2013
    Final Design PS&E Received 07/15/2013
    Final Design PS&E to FAPRO 08/21/2013
    Consultant Contract Process NTP Issued 04/06/2011
    Consultant Contract Process Workhours Approved 02/18/2011