TAUNTON- BRIDGE REPLACEMENT, T-01-015, WASHINGTON STREET (SR 140) OVER THE MILL RIVER
The proposed bridge consists of replacing the existing two-span continuous steel stringer bridge carrying Washington Street over the Mill River in Taunton with a single span precast concrete beams superstructure. The existing abutments will be utilized if possible or integral abutments will be constructed behind the existing abutments. The proposed bridge, as per town request, shall be investigated with four eleven foot lanes, compared to the existing two lanes.
Location:
  • City of Taunton
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Stephen Soma
    Estimated Total Contract Cost: $4,988,996.65
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 5
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    • T01015 
    See the Milestone Details tab for additional Project information