Project Description:
WEST BRIDGEWATER- BRIDGE REPLACEMENT, W-18-012, ROUTE 106 (WEST CENTER STREET) OVER THE HOCKOMOCK RIVER
The existing stone arch and reinforced concrete arch carrying West Center Street over the Hockomock River are anticipated to be replaced with a single span superstructure of approximately 65 feet. The superstructure system of first choice is a precast arch.
Location:
  • Town of West Bridgewater
  • Resident Engineer: Kenneth Belgrave
    Construction Bid Price: $4,059,452.45
    District: District 5

    Contracts (4) Progress
    # 64319 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 68940 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to MassDOT on a task order basis for Layout and Right of Way assignments. Final
    # 77863 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 90847 -- Construction Contract
    Bridge Replacement Br. No. W-18-012 Route 106 (West Center Street) over the Hockomock River (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/25/2016
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/02/2008
    Project Initiation Form PIF Entered 02/03/2009
    Project Initiation Form PRC Submitted 02/03/2009
    Project Review Committee PRC Approved 02/12/2009
    Project Review Committee Letter 02/27/2009
    Project Status Advertised 09/26/2015
    Project Management
    100% Design 100% Package Received 12/17/2014
    100% Design 100% Package Comments to DE 02/02/2015
    25% Design 25% Package Received 08/06/2013
    25% Design 25% Package Received 02/25/2014
    25% Design 25% Package Comments to DE 10/18/2013
    25% Design 25% Package Comments to DE 10/18/2013
    25% Design 25% Package Comments to DE 04/02/2014
    25% Design Design Public Hearing 05/27/2014
    75% Design 75% Package Received 07/24/2014
    75% Design 75% Package Comments to DE 11/04/2014
    Final Design PS&E Received 04/01/2015
    Final Design PS&E Received 01/06/2016
    Final Design PS&E Received 04/04/2016
    Final Design PS&E to FAPRO 09/21/2015
    Final Design PS&E to FAPRO 02/10/2016
    Consultant Contract Process Scope to DE 04/18/2011
    Consultant Contract Process NTP Issued 10/10/2011