Project Description:
DISTRICT 5- SCHEDULED & EMERGENCY REPAIRS TO SUBSTRUCTURES AT VARIOUS LOCATIONS ON ROUTE 24 CORRIDOR
The purpose of this contract is to address substructure deficiencies on bridges located along the Route 24 corridor in District 5.
Location:
Resident Engineer: Alex Lustikman
Construction Contract Value: $2,800,243.00
Construction Bid Price: $2,290,042.50
Initial Construction Estimate: $2,089,343.25
District: District 5

Contracts (1) Progress
# 57636 -- Construction Contract
Scheduled and emergency Bridge Substructure Repairs Along the Route24 Corridor. Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/10/2009
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/04/2008
    Project Initiation Form PIF Entered 10/22/2008
    Project Initiation Form PRC Submitted 11/07/2008
    Project Review Committee PRC Approved 02/12/2009
    Project Status Advertised 12/06/2008
    Project Management
    Final Design PS&E Received 10/23/2008
    Final Design PS&E to FAPRO 11/17/2008
    Consultant Contract Process NTP Issued 07/23/2008