DISTRICT 5- SCHEDULED & EMERGENCY BRIDGE SHIELDING AT VARIOUS LOCATIONS
This District 5-wide Bridge Shielding Contract provides a mechanism to shield bridge decks to prevent loose/delaminated concrete/materials from falling onto areas below.
Location:
Resident Engineer: Gregory Wood
Construction Contract Value: $1,138,479.50
Construction Bid Price: $824,150.00
Initial Construction Estimate: $765,775.00
District: District 5

Contracts (1) Progress
# 57963 -- Construction Contract
Scheduled and Emergency Bridge Shielding Systems at Various Locations Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 04/16/2009
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/04/2008
    Project Initiation Form PIF Entered 10/10/2008
    Project Initiation Form PRC Submitted 10/22/2008
    Project Status Advertised 12/27/2008
    Project Management
    Final Design PS&E Received 10/01/2008
    Final Design PS&E to FAPRO 10/17/2008