Project Description: |
LOWELL- HAMILTON CANAL WALKWAY CONSTRUCTION & REHAB OF L-15-100 (RAILROAD PEDESTRIAN BRIDGE)
The project includes the conversion of an existing trolley bridge into a pedestrian bridge over Swamps Locks Basin in Lowell. Historic bridge railing will be installed as part of the bridge work. Also included in the project is the construction of a walkway along Hamilton Canal between Thorndike Street and Revere Street.
|
Location: |
|
Resident Engineer: | Daniel Boland |
Construction Contract Value: | $2,209,380.00 |
Construction Bid Price: | $1,986,755.00 |
Initial Construction Estimate: | $2,075,367.75 |
District: | District 4 |
|
Bridges
|
|
|
|
|