Project Description:
FAIRHAVEN- SIGNAL & INTERSECTION IMPROVEMENTS ON HUTTLESTON AVENUE (ROUTE 6) AT 4 LOCATIONS: MIDDLE STREET, MAIN STREET, GREEN STREET & ADAMS STREET
The project will include reconstruction of new traffic signal systems in Fairhaven at four intersections along Huttleston Avenue (Middle Street, Main Street, Green Street and Adams Street). Work will include resurfacing the road and constructing new sidewalks with ADA compliant wheelchair ramps. The new traffic signals systems will be coordinated and include phasing to improve safety and congestion along the Huttleson Avenue (Route 6) corridor.
Location:
  • Town of Fairhaven
  • Resident Engineer: Richard McKenzie
    Construction Contract Value: $2,413,217.00
    Construction Bid Price: $2,049,934.00
    Initial Construction Estimate: $2,188,308.00
    District: District 5

    Contracts (4) Progress
    # 57726 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 57792 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design services to the MassHigway on an open end basis located in the Southeast Regional Planning region. Final
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 70924 -- Construction Contract
    Intersection Improvements and Related Work (Including Traffic Signals) on a Section of Route 6 (Huttleston Avenue) at Middle, Main, Green and Adams Streets. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/13/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/10/2008
    Project Initiation Form PIF Entered 09/10/2008
    Project Initiation Form PRC Submitted 09/30/2008
    Project Review Committee PRC Approved 11/06/2008
    Project Review Committee Letter 11/19/2008
    Project Status Advertised 09/03/2011
    Project Management
    100% Design 100% Package Received 06/14/2011
    100% Design 100% Package Comments to DE 08/01/2011
    25% Design 25% Package Received 07/15/2009
    25% Design 25% Package Comments to DE 05/25/2010
    25% Design Design Public Hearing 10/21/2010
    75% Design 75% Package Received 03/11/2011
    75% Design 75% Package Comments to DE 05/10/2011
    Final Design PS&E Received 08/16/2011
    Final Design PS&E Received 08/26/2011
    Final Design PS&E to FAPRO 08/31/2011
    Consultant Contract Process Scope to DE 09/10/2010
    Consultant Contract Process NTP Issued 11/12/2010