Project Description:
NORTH ATTLEBOROUGH- TRAFFIC SIGNAL AND INTERSECTION IMPROVEMENTS @ EAST WASHINGTON STREET (ROUTE 1) & CHESTNUT STREET
Work on this project consists of traffic signal reconstruction and minor geometric improvements at the intersection of Route 1 (East Washington) at Chestnut Street. Currently the intersection does not accommodate the high west bound left-turning volume.
Location:
  • Town of North Attleborough
  • Construction Begins: Spring 2018
    Resident Engineer: Brian Lewis
    Construction Bid Price: $1,187,760.06
    District: District 5

    Contracts (3) Progress
    # 102066 -- Construction Contract
    Intersection Improvements and Related Work (Including Signals) at Route 1 (East Washington) and Chestnut Streets Completed
    # 64321 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77884 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/23/2018
    Contract Information
    Project Designer: Consultant
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/12/2008
    Project Initiation Form PIF Entered 09/15/2008
    Project Initiation Form PRC Submitted 04/22/2009
    Project Review Committee PRC Approved 05/15/2009
    Project Review Committee Letter 06/09/2009
    Project Status Advertised 08/26/2017
    Project Management
    100% Design 100% Package Received 04/07/2015
    100% Design 100% Package Comments to DE 05/15/2015
    100% Design 100% Plans Approved 05/15/2017
    25% Design 25% Package Received 07/25/2013
    25% Design 25% Package Comments to DE 03/14/2014
    25% Design Design Public Hearing 07/24/2014
    Final Design PS&E Received 08/02/2016
    Final Design PS&E to Peer Reviewer 08/16/2016
    Final Design Peer Review Comments to DE 08/19/2016
    Final Design PS&E Received - Resub 1 09/08/2016
    Final Design PS&E Received - Resub 2 11/22/2016
    Final Design PS&E Received - Resub 3 12/14/2016
    Final Design PS&E Received - Resub 4 05/26/2017
    Final Design PS&E Received - Resub 5 05/26/2017