DENNIS- RECONSTRUCTION ON EAST WEST DENNIS ROAD (ROUTE 134) FROM MAIN STREET (ROUTE 28) TO UPPER COUNTY ROAD
Work on this project includes milling, resurfacing and full depth roadway reconstruction of Route 134 from Route 28 to Upper County Road. The proposed cross section will provide 2-11 foot travel lanes and 2-5 foot shoulders/bike lanes, and a 5 foot ADA/AAB compliant walk on the east side of Route 134. Additional proposed work includes traffic signal upgrades at the Upper County Road intersection, drainage improvements, guard rail upgrades, pavement markings and signage installation.
Location:
  • Town of Dennis
  • Resident Engineer: Malcolm Lavalley
    Construction Contract Value: $3,862,027.50
    Construction Bid Price: $3,459,145.50
    Initial Construction Estimate: $3,703,461.64
    District: District 5

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 73648 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Traffic Signals) on a Section of East West Dennis Road (Route 134). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 09/14/2012
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/16/2008
    Project Initiation Form PIF Entered 10/01/2008
    Project Initiation Form PRC Submitted 10/01/2008
    Project Review Committee PRC Approved 11/06/2008
    Project Review Committee Letter 11/25/2008
    Project Status Advertised 05/19/2012
    Project Management
    100% Design 100% Package Received 01/30/2012
    100% Design 100% Package Comments to DE 03/13/2012
    25% Design 25% Package Received 12/01/2010
    25% Design 25% Package Comments to DE 02/18/2011
    25% Design Design Public Hearing 06/30/2011
    75% Design 75% Package Received 08/30/2011
    75% Design 75% Package Comments to DE 11/30/2011
    Final Design PS&E Received 04/25/2012
    Final Design PS&E to FAPRO 05/16/2012