Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 5- TREE REMOVAL & TRIMMING ON MARTHA'S VINEYARD ISLAND
Tree removal and trimming at various locations on Martha's Vineyard Island.
Location:
Resident Engineer: Stephen Soares
Construction Contract Value: $218,871.00
Construction Bid Price: $187,671.00
Initial Construction Estimate: $335,450.00
District: District 5

Contracts (1) Progress
# 58615 -- Construction Contract
Tree Removal and Trimming on Matha's Vineyard only. Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/08/2009
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/16/2008
    Project Initiation Form PIF Entered 09/16/2008
    Project Initiation Form PRC Submitted 09/16/2008
    Project Status Advertised 03/21/2009
    Project Management
    Final Design PS&E Received 12/31/2008
    Final Design PS&E to FAPRO 03/13/2009