Project Description:
MILLBURY- RECONSTRUCTION ON MCCRACKEN ROAD & GREENWOOD STREET, INCLUDES REHAB OF M-22-058, MCCRACKEN ROAD OVER ACCESS ROAD
The proposed project includes reconstruction, modifications to the horizontal and vertical alignment of McCracken Road, widening and geometric improvements to the intersection of Route 122 and McCracken Road, roundabout construction at Greenwood Street and McCracken Road, drainage improvements, sidewalk construction, retaining wall construction and widening the bridge carrying McCracken Road over the access road in the Town of Millbury.
Location:
  • Town of Millbury
  • Construction Begins: Summer 2022
    Resident Engineer: Christopher Jakubiak
    Construction Bid Price: $11,408,210.55
    District: District 3

    Contracts (2) Progress
    # 115769 -- Design -- Services
    Statewide - Master Service Agreement for design and review services. Final
    # 117899 -- Construction Contract
    Roadway Reconstruction and Related Work (Including Roundabout Construction) on a Section of McCracken Road and Intersections with Main (Route 122A) and Greenwood Streets

    Bridges

    Contract Dates
    Notice to Proceed: 09/07/2022
    Contract Information
    Project Designer: Municipality
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 09/18/2008
    Project Initiation Form PIF Entered 09/18/2008
    Project Initiation Form PRC Submitted 04/13/2009
    Project Review Committee PRC Approved 05/14/2009
    Project Review Committee Letter 01/05/2010
    Project Status Advertised 04/30/2022
    Project Management
    100% Design 100% Package Received 07/22/2020
    25% Design 25% Package Received 09/18/2014
    25% Design 25% Package Comments to DE 11/14/2017
    25% Design 25% Package Received - Resub 1 08/10/2018
    25% Design Design Public Hearing 12/18/2018
    75% Design 75% Package Received 10/03/2019
    75% Design 75% Package Comments to DE 12/09/2019
    Final Design PS&E Received 03/09/2022
    Final Design PS&E to FAPRO 04/04/2022