Project Description:
AGAWAM- WEST SPRINGFIELD- BRIDGE REPLACEMENT, A-05-002=W-21-014, ROUTE 147 OVER THE WESTFIELD RIVER & INTERSECTION & SIGNAL IMPROVEMENTS @ 3 LOCATIONS
The purpose of this project is to reconstruct/widen the Rte 147 Bridge over the Westfield River along with intersection reconstruction and new traffic signals at 3 adjacent locations (including connecting roadway) is required to relieve congestion.
Location:
  • City of Agawam
  • Town of West Springfield
  • Construction Begins: Summer 2018
    Resident Engineer: Anna Jenks
    Construction Bid Price: $21,475,105.00
    District: District 2

    Contracts (4) Progress
    # 102272 -- Construction Contract
    Bridge Replacement Br. No. A-05-002=W-21-014 (Steel) Route 147 (Memorial Avenue) over the Westfield River and Intersection Improvements (Including Signals) at 3 Locations alo Completed
    # 64317 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 77846 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77887 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 08/01/2018
    Contract Information
    Project Designer: Consultant
    Funding Source: FED. AID. ACCELERATED BRIDGE
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/01/2008
    Project Initiation Form PIF Entered 10/01/2008
    Project Initiation Form PRC Submitted 10/07/2008
    Project Review Committee PRC Approved 11/06/2008
    Project Review Committee Letter 11/25/2008
    Project Status Advertised 09/16/2017
    Project Management
    100% Design 100% Package Received 03/22/2017
    100% Design 100% Package Comments to DE 05/12/2017
    25% Design 25% Package Received 02/22/2016
    25% Design 25% Package Comments to DE 03/04/2016
    25% Design 25% Package Comments to DE 06/21/2016
    25% Design 25% Package Received - Resub 2 05/25/2016
    25% Design Design Public Hearing 09/08/2016
    75% Design 75% Package Received 12/20/2016
    Final Design PS&E Received 07/10/2017
    Final Design PS&E to Peer Reviewer 07/26/2017
    Final Design Peer Review Comments to DE 08/08/2017
    Final Design PS&E to FAPRO 09/05/2017
    Final Design PS&E Received - Resub 1 04/25/2018