Project Description:
DUDLEY- ROADWAY RECONSTRUCTION AND RELATED WORK ALONG A SECTION OF CENTER ROAD; FAP NO. STP-002S(718)X
The purpose of this Center Road resurfacing project in Dudley includes resurfacing the roadway, providing 11' lanes with 4' shoulders, constructing sidewalks and crosswalks and installing traffic calming measures, as deemed appropriate.
Location:
  • Town of Dudley
  • Resident Engineer: Peter Kurt
    Construction Contract Value: $2,659,739.42
    Construction Bid Price: $2,341,576.75
    Initial Construction Estimate: $2,356,390.00
    District: District 3

    Contracts (1) Progress
    # 84985 -- Construction Contract
    Roadway Reconstruction and Related Work along a Section of Center Road Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/20/2015
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/06/2008
    Project Initiation Form PIF Entered 10/06/2008
    Project Initiation Form PRC Submitted 11/05/2008
    Project Review Committee PRC Approved 11/06/2008
    Project Review Committee Letter 11/18/2008
    Project Status Advertised 09/13/2014
    Project Management
    100% Design 100% Package Received 05/16/2014
    100% Design 100% Package Comments to DE 07/01/2014
    25% Design 25% Package Received 07/30/2010
    25% Design 25% Package Comments to DE 09/14/2012
    25% Design Design Public Hearing 12/05/2012
    75% Design 75% Package Received 09/03/2013
    75% Design 75% Package Comments to DE 01/16/2014
    Final Design PS&E Received 08/12/2014
    Final Design PS&E to FAPRO 09/10/2014