Project Description:
LEOMINSTER- INTERSECTION & SIGNAL IMPROVEMENTS AT MERRIAM AVENUE AND LINDELL AVENUE
The proposed work for the Merriam and Lindell Avenue project in Leominster includes resurfacing and minor roadway widening to accommodate turning movements, updated traffic signal equipment, ADA compliant wheelchair ramps and cement concrete sidewalks, vertical granite curbing and minor drainage work. All new signing and striping would be included as part of the project.
Location:
  • City of Leominster
  • Resident Engineer: Lisa Spezzaferro-Pelleti
    Construction Contract Value: $569,166.00
    Construction Bid Price: $487,333.00
    Initial Construction Estimate: $535,950.50
    District: District 3

    Contracts (2) Progress
    # 64304 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 71948 -- Construction Contract
    Intersection Improvements and Related Work (Including Traffic Signals) - Merriam Avenue at Lindell Avenue. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/15/2012
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/07/2008
    Project Initiation Form PIF Entered 10/07/2008
    Project Initiation Form PRC Submitted 11/05/2008
    Project Review Committee PRC Approved 11/06/2008
    Project Review Committee Letter 11/18/2008
    Project Status Advertised 11/19/2011
    Project Management
    100% Design 100% Package Received 08/26/2011
    100% Design 100% Package Comments to DE 11/01/2011
    25% Design 25% Package Received 06/04/2010
    25% Design 25% Package Comments to DE 09/22/2010
    25% Design Design Public Hearing 11/16/2010
    75% Design 75% Package Received 02/02/2011
    75% Design 75% Package Comments to DE 05/03/2011
    Final Design PS&E Received 11/14/2011
    Final Design PS&E to FAPRO 11/15/2011