Project Description:
LANCASTER- INTERSECTION IMPROVEMENTS @ FIVE CORNERS: ROUTE 110 (BOLTON ROAD, HIGH STREET EXTENSION), CENTER BRIDGE ROAD, OLD COMMON ROAD
The Lancaster Five Corners project involves relocating Bolton Road to remove one leg of the intersection. The project also includes upgraded traffic control, minor geometric modifications, improved signage, and pavement markings.
Location:
  • Town of Lancaster
  • Resident Engineer: Steven Miller
    Construction Contract Value: $1,116,392.00
    Construction Bid Price: $981,322.00
    Initial Construction Estimate: $1,103,920.00
    District: District 3

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 78209 -- Construction Contract
    Roadway Reconstruction and Related Work at the Intersection of Route 110 (High Street Extension), Center Bridge, Old Common and Bolton Roads. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/20/2013
    Contract Information
    Project Designer: Municipality
    Funding Source: CONGESTION MIT. AIR QUAL.
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/07/2008
    Project Initiation Form PIF Entered 10/07/2008
    Project Initiation Form PRC Submitted 11/05/2008
    Project Review Committee PRC Approved 11/06/2008
    Project Review Committee Letter 11/18/2008
    Project Status Advertised 06/29/2013
    Project Management
    100% Design 100% Package Received 10/26/2012
    100% Design 100% Package Comments to DE 01/25/2013
    25% Design 25% Package Received 10/07/2009
    25% Design 25% Package Comments to DE 04/13/2010
    25% Design Design Public Hearing 06/14/2010
    75% Design 75% Package Received 01/18/2011
    75% Design 75% Package Comments to DE 04/25/2012
    Final Design PS&E Received 06/06/2013
    Final Design PS&E to FAPRO 06/26/2013