DISTRICT 5- DUMPING GROUND CLOSURES AT VARIOUS LOCATIONS IN SHARON, WALPOLE & WRENTHAM
Proejct consist of the excavation of solid waste dumping areas at various MassHigway Maintenance Depots. Work includes excavation and removal of waste, filling and regrading of dumping areas.
Location:
Resident Engineer: Jeffrey Peterson
Construction Contract Value: $720,773.75
Construction Bid Price: $356,619.00
Initial Construction Estimate: $499,246.05
District: District 5

Contracts (2) Progress
# 55607 -- Design -- HazMat
Work will consist of construction oversight and closure certification at 10 illicit solid waste dumping sites located at locations in Districts 1,3, 4,5. Final
# 57519 -- Construction Contract
Dumping Ground Closures at 2 Locations. Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/16/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/09/2008
    Project Initiation Form PIF Entered 10/09/2008
    Project Initiation Form PRC Submitted 10/09/2008
    Project Review Committee PRC Approved 03/12/2007
    Project Status Advertised 11/01/2008
    Project Status Advertised 01/10/2009
    Project Management
    Final Design PS&E Received 08/28/2008
    Final Design PS&E to FAPRO 10/20/2008