Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
WILMINGTON- METHUEN- GUIDE & TRAFFIC SIGN REPLACEMENT ON I-93, FROM SR129 (EXIT 38) TO SR213 (EXIT 48)
This project will entail the replacement of all guide, regulatory, and warning signs on Interstate Route 93 from State Route 129 (Exit 38) in Wilmington northerly to State Route 213 (Exit 48) in Methuen, including applicable signing on intersecting secondary roadways.
Location:
  • Town of Methuen
  • Town of Wilmington
  • Resident Engineer: Mark Spinale
    Construction Contract Value: $3,995,720.03
    Construction Bid Price: $3,161,888.85
    Initial Construction Estimate: $4,181,421.00
    District: District 4

    Contracts (1) Progress
    # 64076 -- Construction Contract
    Guide and Traffic Sign Replacement along Interstate I-93. RE-ADVERTISED 100% Complete

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 08/11/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/09/2008
    Project Initiation Form PIF Entered 10/09/2008
    Project Initiation Form PRC Submitted 10/09/2008
    Project Review Committee PRC Approved 03/13/2007
    Project Review Committee Letter 02/23/2009
    Project Status Advertised 08/08/2009
    Project Status Advertised 04/24/2010
    Project Management
    100% Design 100% Package Received 03/06/2009
    25% Design 25% Package Comments to DE 03/11/2008
    25% Design 25% Package Approved 03/07/2008
    75% Design 75% Package Received 10/06/2008
    75% Design 75% Package Comments to DE 01/26/2009
    75% Design 75% Plans Approved 01/23/2009
    Final Design PS&E Received 04/15/2010
    Final Design PS&E to FAPRO 04/16/2010
    Consultant Contract Process Scope to DE 05/24/2007
    Consultant Contract Process NTP Issued 07/09/2007