BECKET- CHESTER- BRIDGE REPLACEMENTS, B-03-008, B-03-010, B-03-011, B-03-037 & C-11-033 (US ROUTE 20), JACOB'S LADDER ROAD OVER WALKER BROOK & US ROUTE 20 OVER CUSHMAN BROOK & WALKER BROOK
The proposed project consists of the full replacement of FIVE bridges in Becket and Chester carrying Route 20 (Jacobs Ladder Rd.) over Walker Brook and Route 20 over Cushman & Walker Brook. This project was bundled with Project No. 605440 into one construction contract.
Location:
  • Town of Becket
  • Town of Chester
  • Resident Engineer: Matthew Fillio
    Construction Contract Value: $10,888,801.59
    Construction Bid Price: $9,421,566.85
    Initial Construction Estimate: $10,176,876.15
    District: District 1

    Contracts (3) Progress
    # 57467 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 66702 -- Design -- Geotechnical
    Work will consist of Geotechnical design and review services for roadway and bridge projects statewide. Final
    # 71085 -- Construction Contract
    5 Bridge Replacement (B-03-008, B-03-010-, B-03-011,B-03-037 & C-11-033 (Concrete) - Route 20 (Jacobs Ladder Road) over Cushman and Walker Brooks. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/09/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/20/2008
    Project Initiation Form PIF Entered 02/10/2009
    Project Initiation Form PRC Submitted 02/10/2009
    Project Review Committee PRC Approved 02/12/2009
    Project Review Committee Letter 09/10/2009
    Project Status Advertised 09/17/2011
    Project Management
    25% Design 25% Package Received 12/22/2010
    25% Design 25% Package Received 04/01/2011
    25% Design 25% Package Comments to DE 01/10/2011
    25% Design 25% Package Comments to DE 01/11/2011
    25% Design 25% Package Comments to DE 01/13/2011
    25% Design 25% Package Comments to DE 01/14/2011
    25% Design 25% Package Comments to DE 01/24/2011
    25% Design 25% Package Comments to DE 01/26/2011
    25% Design 25% Package Comments to DE 01/31/2011
    25% Design 25% Package Comments to DE 03/08/2011
    25% Design 25% Package Approved 01/23/2011
    25% Design Design Public Hearing 03/01/2011
    25% Design 25% Plans Complete 02/25/2011
    75% Design 75% Package Received 06/14/2011
    Final Design PS&E Received 08/19/2011
    Final Design PS&E to FAPRO 09/14/2011
    Consultant Contract Process Scope to DE 08/17/2009
    Consultant Contract Process NTP Issued 10/12/2009
    Consultant Contract Process Workhours Approved 12/02/2009