Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
GRAFTON- BRIDGE REHABILITATION, G-08-007, PLEASANT STREET OVER BLACKSTONE RIVER (ABP-DB1)
Location:
  • Town of Grafton
  • Resident Engineer: Kevin Troy
    Construction Contract Value: $5,000,000.00
    Construction Bid Price: $4,236,603.00
    Initial Construction Estimate: $4,236,603.00
    District: District 3

    Contracts (1) Progress
    # 57664 -- Construction Contract
    Bridge Rehabilitation (G-08-007) - Pleasant Street over the Blackstone River. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 02/04/2009
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/20/2008
    Project Status Advertised 10/18/2008
    Project Management
    Final Design PS&E Received 09/30/2008
    Consultant Contract Process NTP Issued 02/04/2009