Project Description:
LONGMEADOW- WEST SPRINGFIELD- GUIDE & TRAFFIC SIGN REPLACEMENT ON I-91
This project entails the replacement of guide and traffic signs on Interstate Route 91. The replacements will be made from the Connecticut/Massachusetts border in Longmeadow northerly to the US Route 5 interchange (Exits 13A-B) in West Springfield, including applicable signing on intersecting secondary roadways. Most of the signs are about 15 years old and reaching the end of their service life.
Location:
  • Town of Longmeadow
  • Town of West Springfield
  • Resident Engineer: Joseph Hogan
    Construction Contract Value: $4,140,930.65
    Construction Bid Price: $3,569,118.70
    Initial Construction Estimate: $5,203,618.00
    District: District 2

    Contracts (1) Progress
    # 72265 -- Construction Contract
    Guide and Traffic Sign Replacement along a Section of Interstate 91. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 06/08/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 10/21/2008
    Project Initiation Form PIF Entered 10/21/2008
    Project Initiation Form PRC Submitted 10/21/2008
    Project Review Committee PRC Approved 02/12/2009
    Project Review Committee Letter 02/23/2009
    Project Status Advertised 12/24/2011
    Project Management
    100% Design 100% Package Received 11/08/2010
    25% Design 25% Package Received 07/17/2009
    25% Design 25% Package Comments to DE 09/21/2009
    25% Design 25% Package Approved 09/18/2009
    75% Design 75% Package Received 07/02/2010
    75% Design 75% Package Comments to DE 08/18/2010
    75% Design 75% Plans Approved 08/17/2010
    Final Design PS&E Received 11/14/2011
    Final Design PS&E to FAPRO 12/19/2011
    Consultant Contract Process Scope to DE 10/23/2008
    Consultant Contract Process NTP Issued 01/30/2009
    Consultant Contract Process Workhours Approved 01/30/2009