| Project Description: |
DISTRICT 4- SCHEDULED & EMERGENCY SUBSTRUCTURE REPAIRS (ESSEX & MIDDLESEX)
Removal of deteriorated concrete from stem piers, pier caps, pier columns, wing walls, back walls and abutments and replacing excavated concrete and damaged reinforcing steel with new materials as specified. Replacing existing mising or damaged underbridge slope paving with cement concrete slope paving as directed by the Engineer.
|
| Location: | |
| Resident Engineer: | Thomas Zizza![]() |
| Construction Contract Value: | $2,654,700.00 |
| Construction Bid Price: | $2,294,700.00 |
| Initial Construction Estimate: | $1,892,287.50 |
| District: | District 4 |
|