Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
DISTRICT 3- TREE TRIMMING & REMOVAL AT VARIOUS LOCATIONS
The contract is for the removal and pruning of trees on State Highway Layout. The work is needed to restore the clear zone and provide sight distance.
Location:
Resident Engineer: Joel Babcock
Construction Contract Value: $1,439,065.00
Construction Bid Price: $1,379,065.00
Initial Construction Estimate: $1,437,000.00
District: District 3

Contracts (1) Progress
# 58087 -- Construction Contract
Tree Trimming and Removal at Various Locations Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/18/2009
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/05/2008
    Project Initiation Form PIF Entered 11/05/2008
    Project Initiation Form PRC Submitted 11/05/2008
    Project Review Committee PRC Approved 02/12/2009
    Project Review Committee Letter 02/13/2009
    Project Status Advertised 02/14/2009
    Project Management
    Final Design PS&E Received 12/24/2008