Project Description:
READING- BRIDGE PRESERVATION, R-03-011, I-93 OVER I-95 (ST 128)
The work for the bridge carrying Route I-93 over I-95 shall consist of upgrading the approach guard rail; removing and replacing the filler joints over the abutments; repairing the existing beams; repairing the existing abutments; removing and resetting the existing slope paving where it has settled; stripping and painting steel as needed. Provisions for the new approach guard rail shall be made at the four corners of the bridge. Spalling and cracks at the breastwall and the beam seat areas on the abutments shall be repaired as required.
Location:
  • Town of Reading
  • Design Responsibility: Consultant
    Project Manager: M. Ali Jalinous
    Estimated Total Contract Cost: $4,249,300.00
    Estimated Total Federal Participating Construction Cost: $4,635,600.00
    District: District 4
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/05/2008
    Project Initiation Form PIF Entered 11/05/2008
    Project Initiation Form PRC Submitted 11/05/2008
    Project Review Committee PRC Approved 11/06/2008
    Project Management