BUCKLAND- SHELBURNE- BRIDGE BETTERMENT, B-28-032=S-11-014, ROUTE 2 OVER ROUTE 112 & DEERFIELD RIVER
The proposed work on the bridges carrying Route 2 over Route 112 and the Deerfield River shall consist of removing the wearing surface and membrane waterproofing on the bridge; replacing the concrete deck slab; reconstructing the approach wearing surface; removing and replacing the bridge bearings railing; repairing deteriorated superstructure elements; repairing the existing substructure; and stripping and painting the steel.
Location:
  • Town of Buckland
  • Town of Shelburne
  • Design Responsibility: Consultant
    Right of Way Responsibility: MassDOT
    Project Manager: Kenneth L Lamontagne
    Estimated Total Contract Cost: $7,650,472.00
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 1
    Current Status: This project is in the preliminary design phase.

    Contracts (0) Progress
    No contracts associated with this project

    Bridges

    • B28032 
    See the Milestone Details tab for additional Project information