Project Description:
HUNTINGTON- BRIDGE REPLACEMENT, H-27-006, (CSX DESIGN/BUILD - ABP-CSX2)
This project shall consist of superstructure replacement of the portion of Bridge that carries State Route 112 Worthington Road over the CSX tracks in Huntington. This bridge project is part of a program to elevate the highway bridge vertical clearance to 21 feet over rail tracks at fourteen crossings, between the Worcester and the New York line. This will allow double stack freight trains to travel on this important segment of the CSX rail line.
Location:
  • Town of Huntington
  • Resident Engineer: Richard Miskinis Jr
    Construction Contract Value: $4,902,800.00
    Construction Bid Price: $4,156,000.00
    Initial Construction Estimate: $3,748,882.00
    District: District 1

    Contracts (3) Progress
    # 49402 -- Design -- Hwy Eng Open End
    Work will generally consist of providing design and engineering services to the Projects Division on an open end basis for various statewide Value Engineering Studies. Final
    # 57466 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 67757 -- Construction Contract
    Worthington Road (SR 112) Bridge Replacement (H-27-006) (ABP-CSX) over the CSX Railroad (ABP) (DESIGN/BUILD) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 04/29/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/06/2008
    Project Initiation Form PIF Entered 02/02/2009
    Project Initiation Form PRC Submitted 02/02/2009
    Project Review Committee PRC Approved 02/21/2009
    Project Review Committee Letter 02/27/2009
    Project Status Advertised 07/10/2010
    Project Management
    25% Design 25% Package Received 02/01/2011