DISTRICT 4- INTERSTATE STRUCTURAL REPAIRS (ABP-PR26)
Location:
Resident Engineer: Thomas Zizza
Construction Contract Value: $3,563,580.50
Construction Bid Price: $1,608,580.50
Initial Construction Estimate: $1,927,000.00
District: District 4

Contracts (1) Progress
# 67060 -- Construction Contract
Scheduled and Emergency Bridge Repairs at Various Locations. (ABP) Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/25/2011
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/06/2008
    Project Status Advertised 09/25/2010
    Project Management
    100% Design 100% Package Received 09/01/2010
    Final Design PS&E Received 09/17/2010
    Final Design PS&E to FAPRO 09/21/2010