Project Description:
LITTLETON- BRIDGE BETTERMENT, L-13-026, ROUTE 2A (KING STREET) OVER I-495
The project to improve the Route 2A bridge over I-495 shall consist of reconstructing the bridge and approach wearing surface; removal and replacement of the reinforced concrete deck slab; upgrading the bridge rail; upgrading the approach guard rail; removal and replacement of the joints over the pier 2 & 4 with the Asphaltic joint and joint over pier 1 & 3 with link-slab; Check the existing beams cover plates for fatigue and provide modification as needed; repair the existing abutments backwall and breastwall, beams pedestals, deteriorated area of pier cap and spalled/delamination area on the columns; remove and reset the existing rip-raps where it has settled; Clean and paint the structural steel (Over coat) and localized (Full paint) as directed by the engineer.
Location:
  • Town of Littleton
  • Resident Engineer: Arvind Patel
    Construction Contract Value: $3,554,690.00
    Construction Bid Price: $3,045,682.00
    Initial Construction Estimate: $4,036,430.00
    District: District 3

    Contracts (4) Progress
    # 57726 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various highway and bridge projects. Final
    # 64303 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 66460 -- Construction Contract
    Bridge Rehabilitation (Including Painting) (L-13-026) (Steel) - Route 2A (King Street) over Interstate 495 Completed
    # 77847 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 12/01/2010
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/14/2008
    Project Initiation Form PIF Entered 11/14/2008
    Project Initiation Form PRC Submitted 11/14/2008
    Project Review Committee PRC Approved 02/12/2009
    Project Review Committee Letter 02/27/2009
    Project Status Advertised 07/17/2010
    Project Management
    100% Design 100% Package Comments to DE 04/21/2009
    75% Design 75% Package Received 03/10/2009
    Final Design PS&E Received 06/10/2010
    Final Design PS&E to FAPRO 07/13/2010
    Consultant Contract Process Scope to DE 08/20/2008
    Consultant Contract Process NTP Issued 11/19/2008