Project Description:
REVERE- SUPERSTRUCTURE REPLACEMENT & SUBSTRUCTURE REPAIRS, R-05-016, REVERE BEACH PARKWAY OVER BLUE LINE AND STATE ROAD
Location:
  • City of Revere
  • Resident Engineer: John Lepore
    Construction Contract Value: $5,270,412.00
    Construction Bid Price: $4,368,880.00
    Initial Construction Estimate: $4,625,950.00
    District: District 4

    Contracts (3) Progress
    # 57463 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 57467 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 75236 -- Construction Contract
    Bridge Superstructure Replacement using Accelerated Bridge Construction Techniques (R-05-016) - Revere Beach Parkway over MBTA Blue Line and State Road. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 01/29/2013
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/21/2008
    Project Initiation Form PIF Entered 11/21/2008
    Project Initiation Form PRC Submitted 12/01/2009
    Project Review Committee PRC Approved 12/02/2009
    Project Status Advertised 08/25/2012
    Project Management
    100% Design 100% Plans Approved 06/28/2012
    25% Design 25% Package Received 06/03/2011
    25% Design 25% Package Approved 02/01/2012
    75% Design 75% Package Received 05/04/2012
    Final Design PS&E Received 08/16/2012
    Final Design PS&E to FAPRO 08/22/2012
    Consultant Contract Process NTP Issued 11/03/2010