Project Description:
NEWTON- WESTON- BRIDGE REHABILITATION, N-12-080=W-29-064, RIVERSIDE PARK PEDESTRIAN BRIDGE OVER CHARLES RIVER
The purpose of this project is to restore the Newton Riverside Pedestrian Foot Bridge over the Charles River for pedestrian use. Remove existing timber deck and railing. Construct new preservative timber deck and railing. Clean and paint existing structural steel. Perform scour investigation and provision of scour counter measures if required. Total replacement of the West abutment due to erosion.
Location:
  • City of Newton
  • Town of Weston
  • Resident Engineer: Ahmad Ilyas
    Construction Contract Value: $1,104,418.00
    Construction Bid Price: $942,659.50
    Initial Construction Estimate: $1,246,411.00
    District: District 6

    Contracts (2) Progress
    # 64321 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 70937 -- Construction Contract
    Bridge Rehabilitation (Including Painting) Br. No. N-12-080=W-29-064 Riverside Park Pedestrian Bridge over the Charles River. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 02/16/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/21/2008
    Project Initiation Form PIF Entered 11/21/2008
    Project Initiation Form PRC Submitted 12/09/2009
    Project Review Committee PRC Approved 12/02/2009
    Project Status Advertised 09/03/2011
    Project Management
    100% Design 100% Package Received 08/18/2011
    75% Design 75% Package Received 09/27/2010
    Final Design PS&E Received 08/18/2011
    Final Design PS&E to FAPRO 08/30/2011