Project Description:
BOSTON- BRIDGE REHABILITATION, B-16-381, HUGH FARREN PEDESTRIAN BRIDGE OVER OLD COLONY AVENUE
The project consists of the rehabilitation of the existing pedestrian bridge over Old Colony Avenue in the City of Boston, MA. The project extends approximately 250 feet north and south from the bridge crossing and includes resetting existing granite curb, new granite curb, replacement of existing cement concrete walk, installation of new brick pavers, minor drainage improvements, landscaping, resetting existing ornamental lighting, new signs, new pavement markings, and other incidental items of work.
Location:
  • City of Boston
  • Resident Engineer: Carmen Ciampi
    Construction Contract Value: $1,794,587.00
    Construction Bid Price: $1,532,502.00
    Initial Construction Estimate: $1,336,887.00
    District: District 6

    Contracts (3) Progress
    # 57467 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 60283 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassHighway on an open end basis for various statewide highway and bridge ABP projects. Final
    # 70723 -- Construction Contract
    Bridge Rehabilitation (Including Painting) (B-16-381) Hugh Farren Pedestrian Bridge over Old Colony Avenue. (ABP) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 02/16/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/21/2008
    Project Initiation Form PIF Entered 11/21/2008
    Project Status Advertised 08/27/2011
    Project Management
    25% Design 25% Package Received 09/23/2010
    75% Design 75% Package Received 06/01/2011
    Final Design PS&E Received 08/10/2011
    Final Design PS&E to FAPRO 08/24/2011
    Consultant Contract Process NTP Issued 04/06/2010