Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BOSTON- CAMBRIDGE- BRIDGE REHABILITATION OF ANDERSON MEMORIAL BRIDGE, B-16-011=C-01-007, NORTH HARVARD STREET OVER CHARLES RIVER
DCR23 - Anderson Memorial Bridge - Rehabilitation project. Rehabilitation needs based on present conditions assessment include retainage of existing piers and abutments, rehabilitation or replacement of existing arches and replacement of spandrel and approach walls, parapets and lighting.
Location:
  • City of Boston
  • City of Cambridge
  • Resident Engineer: Roderick Connelly III
    Construction Contract Value: $25,536,864.00
    Construction Bid Price: $19,983,892.00
    Initial Construction Estimate: $19,437,560.00
    District: District 6

    Contracts (6) Progress
    # 54837 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 57462 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 68385 -- Design -- Bridge Open End
    Work will consist of providing engineering design and review services to MassDOT on an open end basis for various statewide highway and bridge projects. Final
    # 70935 -- Construction Contract
    Bridge Rehabilitation Br. No. B-16-011=C-01-007 (Concrete) (Larz Anderson Memorial Bridge) North Harvard Street over the Charles River. (ABP) Completed
    # 77859 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final
    # 77864 -- Design -- Hwy Eng Open End
    Master Service Agreement for statewide design and review services. Final

    Bridges

    Contract Dates
    Notice to Proceed: 03/09/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Initiation
    no comments
    Scoping
    no comments
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/21/2008
    Project Initiation Form PIF Entered 11/21/2008
    Project Initiation Form PRC Submitted 12/22/2009
    Project Review Committee PRC Approved 12/02/2009
    Project Status Advertised 09/03/2011
    Project Management
    100% Design 100% Package Received 05/17/2011
    25% Design 25% Package Received 06/25/2010
    75% Design 75% Package Received 12/03/2010
    Final Design PS&E Received 08/26/2011
    Final Design PS&E to FAPRO 08/30/2011
    Consultant Contract Process NTP Issued 08/25/2009