Project Description:
CAMBRIDGE- BRIDGE REPLACEMENT, C-01-041, MAGAZINE BEACH PEDESTRIAN BRIDGE OVER ROUTE 3 (MEMORIAL DRIVE)
Location:
  • City of Cambridge
  • Resident Engineer: Kathryn Barr
    Construction Contract Value: $4,609,257.25
    Construction Bid Price: $3,593,615.00
    Initial Construction Estimate: $4,067,725.82
    District: District 6

    Contracts (2) Progress
    # 57466 -- Design -- Bridge Open End
    Work will consist of providing engineering design, review and construction management services on a task order basis. Final
    # 61941 -- Construction Contract
    Bridge Replacement (C-01-041) - Magazine Beach Pedestrian Bridge over Route 3 (Memorial Drive). (ABP) - (DCR) Completed

    Bridges

    Contract Dates
    Notice to Proceed: 03/10/2010
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Non Federal Aid
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/21/2008
    Project Initiation Form PIF Entered 11/21/2008
    Project Initiation Form PRC Submitted 03/29/2010
    Project Review Committee PRC Approved 05/13/2010
    Project Status Advertised 09/30/2009
    Project Management
    Consultant Contract Process NTP Issued 12/01/2006