Project Description: |
BOSTON- FULL DECK REPLACEMENT, B-16-390, ROUTE 3A (MORRISSEY BOULEVARD) OVER NEPONSET RIVER (NEPONSET RIVER BRIDGE - PHASE II)
|
Location: |
|
Resident Engineer: | Jahangir Rajabi Dehkharghani |
Construction Contract Value: | $38,772,185.00 |
Construction Bid Price: | $33,714,944.00 |
Initial Construction Estimate: | $45,000,000.00 |
District: | District 6 |
|
Bridges
|
|
|
|
|