| Project Description: | NEWTON- WELLESLEY- BRIDGE REHABILITATION (PED), N-12-086=W-13-026, LOWER FALLS AT CONCORD STREET OVER CHARLES RIVER (P-40)
 Rehabilitation of an abandoned railroad bridge over the Charles River in Newton and Wellesley for use as a pedestrian bridge and the construction of bridge approaches which include trail and amenities to the bridge. The approaches include a permanent bridge approach on the Newton side and an interim bridge approach on the Wellesley side of the bridge. | 
| Location: |  | 
| Resident Engineer: | Kathryn Barr  | 
| Construction Contract Value: | $555,330.00 | 
| Construction Bid Price: | $474,200.00 | 
| Initial Construction Estimate: | $700,000.00 | 
| District: | District 6 | 
| 
 | Bridges
 | ||||||||||||||
| 
 | ||||||||||
| 
 | 
| 
 | 
| 
 
 
 | ||||||||||||||||||||||||||