DCR- BRIDGE PRESERVATION AT VARIOUS LOCATIONS
Location:
Resident Engineer: Alex Anselme
Construction Contract Value: $3,516,299.95
Construction Bid Price: $2,144,600.00
Initial Construction Estimate: $2,361,825.00
District: District 6

Contracts (1) Progress
# 60266 -- Construction Contract
Bridge Preservation at Various Locations (DCR) (ABP) Completed

Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/17/2007
    Contract Information
    Project Designer: Other
    Funding Source:
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 11/26/2008
    Project Management
    Consultant Contract Process NTP Issued 10/01/2008