| Project Description: |
BELCHERTOWN- WARE- RESURFACING & RELATED WORK ON ROUTE 9
The purpose of this project is to resurface portions of Route 9. Work will also include repairs/upgrades to guardrail end treatments as needed and new pavement markings. Bechertown: from Pelham T.L. to Ware T.L. (mile 52.91 - 62.60), Ware: 1000' east of Monson Tpk Rd to End St. Hwy near Vernon St. (mile 64.7-68.5) and from begin St. Hwy. near Ross Ave to W. Brookfied TL (mile 69.8-70.6); a total distance of 14.29 miles.
|
| Location: |
|
| Resident Engineer: | Stefan Toth![]() |
| Construction Contract Value: | $4,794,746.10 |
| Construction Bid Price: | $3,895,070.35 |
| Initial Construction Estimate: | $4,007,765.00 |
| District: | District 2 |
|