Project Description:
BELCHERTOWN- SIGNAL & INTERSECTION IMPROVEMENTS AT MAIN STREET (ROUTE 181), MAPLE STREET (RTE 202), JABISH STREET (ROUTE 21)
This intersection currently provides a good Level of Service (LOS) for 2 of the 3 major approaches but experiences long delays on the Rte 202 (Maple St) eastbound approach and the Rte 21 (Jabish St) westbound minor approach. The overall intersection LOS is F at the PM peak hour. The crash rate (1.1 2003-2005) is above the statewide and District 2 average for a signalized intersection. LOS can be improved throughout the intersection by providing an exclusive left turn lane to the South Main Street NB approach and reconfiguring lane assignments on Maple Street EB. Project will include new signal equipment, minor widening of South Main and Maple Streets, new sidewalks and wheelchair ramps, new and reset granite curb, coldplane-overlay and new striping and signage.
Location:
  • Town of Belchertown
  • Resident Engineer: Richard Wonderlie
    Construction Contract Value: $0.00
    Construction Bid Price: $637,526.00
    Initial Construction Estimate: $643,635.00
    District: District 2

    Contracts (2) Progress
    # 64315 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 72561 -- Construction Contract
    Intersection Improvements and Related Work (Including Traffic Signals) Main Street (Route 181) at Maple (Rte 202) and Jabish Streets. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 07/17/2012
    Contract Information
    Project Designer: Municipality
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/13/2009
    Project Initiation Form PIF Entered 01/13/2009
    Project Initiation Form PRC Submitted 01/15/2009
    Project Review Committee PRC Approved 02/12/2009
    Project Review Committee Letter 02/23/2009
    Project Status Advertised 01/28/2012
    Project Management
    100% Design 100% Package Received 07/11/2011
    100% Design 100% Package Comments to DE 09/20/2011
    25% Design 25% Package Received 08/21/2009
    25% Design Design Public Hearing 06/02/2010
    75% Design 75% Package Received 11/30/2010
    Final Design PS&E Received 01/18/2012
    Final Design PS&E to FAPRO 01/25/2012