BROCKTON- WEST BRIDGEWATER- BRIDGEWATER- RAYNHAM- RESURFACING & RELATED WORK ON ROUTE 24
Work on this project consists of milling and resufracing the entire length of Route 24 in the City of Brockton and the Towns of West Bridgewater, Bridgewater and and approximately 1 mile of work in Raynham.
Location:
  • Town of Bridgewater
  • City of Brockton
  • Town of Raynham
  • Town of West Bridgewater
  • Project Manager: Albert Li
    Estimated Total Contract Cost: $13,543,971.51
    Estimated Total Federal Participating Construction Cost: N/A
    District: District 5
    Current Status: This project is in the preliminary design phase.