AUBURN- BRIDGE DECK REPLACEMENT, A-17-029, SWANSON ROAD OVER I-290
The purpose of this project is to replace the deck and perform necessary substructures repairs to the bridge carrying Swanson Road over I-290 in the Town of Auburn.
Location:
  • Town of Auburn
  • Resident Engineer: Stephen Shamoian
    Construction Contract Value: $2,050,095.00
    Construction Bid Price: $1,769,177.50
    Initial Construction Estimate: $2,354,956.50
    District: District 3

    Contracts (2) Progress
    # 55041 -- Design -- Bridge Rehab/Recon/New Const
    Work will consist of structural evaluations and emergency design support services to support the Bridge Preservation/Betterment Advertisement Program. Final
    # 72306 -- Construction Contract
    Bridge Deck Replacement (A-17-029) (Steel) Swanson Road over Interstate 290. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/11/2012
    Contract Information
    Project Designer: Consultant
    Funding Source: BRR OFF SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/21/2009
    Project Initiation Form PIF Entered 01/21/2009
    Project Initiation Form PRC Submitted 01/26/2009
    Project Review Committee PRC Approved 02/12/2009
    Project Review Committee Letter 03/11/2009
    Project Status Advertised 12/31/2011
    Project Management
    100% Design 100% Package Received 11/30/2011
    100% Design 100% Package Comments to DE 11/30/2011
    100% Design 100% Package Comments to DE 12/19/2011
    25% Design Design Public Hearing 10/18/2011
    75% Design 75% Package Received 05/28/2010
    75% Design 75% Package Comments to DE 06/21/2010
    Final Design PS&E Received 12/27/2011
    Final Design PS&E to FAPRO 12/27/2011