MIDDLEBOROUGH- CABLE BARRIER INSTALLATION ON I-495
Cable barriers will be installed along I-495 Mile Marker 6 to Mile Marker 15.1 for a distance of 9.1 miles. This location has been selected for cable barrier installation because, based on the statewide crash data, it has been identified as the top fatal and incapacitating injury cross median crash locations in the state. A Road Safety Audit (which included field visits, meetings and a formal report) has already been conducted with the State Police, Regional Planning Agency, MassHighway District and Boston offices, FHWA and others. As a result, cable barrier installation has been recommended to reduce the incidence of fatal and injury crashes, which is the overarching goal of the MA Strategic Highway Safety Plan (a multi-agency document prepared in October 2006).
Location:
  • Town of Middleborough
  • Resident Engineer: Kenneth White
    Construction Contract Value: $1,192,156.00
    Construction Bid Price: $1,045,869.60
    Initial Construction Estimate: $1,245,875.00
    District: District 5

    Contracts (1) Progress
    # 60373 -- Construction Contract
    Cable Barrier Installation Along a Section of Route I-495. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/08/2010
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Highway Safety Improvement Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/27/2009
    Project Initiation Form PIF Entered 01/29/2009
    Project Initiation Form PRC Submitted 01/29/2009
    Project Review Committee PRC Approved 02/12/2009
    Project Review Committee Letter 02/23/2009
    Project Status Advertised 09/12/2009
    Project Management
    100% Design 100% Package Received 08/21/2009
    100% Design 100% Package Comments to DE 08/21/2009
    75% Design 75% Package Received 08/04/2009
    Final Design PS&E Received 09/04/2009
    Final Design PS&E to FAPRO 09/04/2009