Project Description:
AUBURN- WORCESTER- INTERSTATE MAINTENANCE & RELATED WORK ON I-395 & I-290
This project consists of resurfacing two sections of I-290 and I-395 in Auburn and Worcester. The first section starts at the Oxford / Auburn town line (I-395 mm 9.8±) and proceeds north to the junction of I-395 and I-290 (I-395 mm 11.8± / I-290 mm 0.0±) and then proceeds east to a pavement joint (I-290 mm 1.2±), which is located in the vicinity of the Swanson Road Bridge over I-290. The second section starts at a pavement joint (I-290 mm 2.8±), which is located just west of the Auburn / Worcester town line and proceeds east to the I-290 Bridge over the Providence and Worcester Railroad (I-290 mm 3.7±). The total length of this project is approximately 5.7 miles. The limits of work also include the ramps at Exits 6A, 6B, 7, 8, 9 and 10, as well as the portion of Auburn Street in Auburn between the on and off ramps at Exit 9.
Location:
  • Town of Auburn
  • City of Worcester
  • Resident Engineer: Roger Wykes
    Construction Contract Value: $10,570,749.00
    Construction Bid Price: $9,191,926.20
    Initial Construction Estimate: $9,588,952.00
    District: District 3

    Contracts (1) Progress
    # 65188 -- Construction Contract
    Resurfacing and Related Work on Sections of Interstates 290 and 395. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 10/18/2010
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/30/2009
    Project Need Form PNF Approved 02/09/2009
    Project Initiation Form PIF Entered 02/10/2009
    Project Initiation Form PRC Submitted 02/17/2009
    Project Review Committee PRC Approved 02/12/2009
    Project Review Committee Letter 02/19/2009
    Project Status Advertised 06/05/2010
    Project Management
    100% Design 100% Package Received 11/24/2009
    100% Design 100% Package Comments to DE 12/04/2009
    75% Design 75% Package Received 11/24/2009
    Final Design PS&E Received 04/05/2010
    Final Design PS&E to FAPRO 04/27/2010