Project Description:
BURLINGTON- WOBURN- INTERSTATE MAINTENANCE & RELATED WORK ON I-95
The project will resurface I-95 in Burlington & Woburn between MM 51.4 and MM 53.4 for a total project length of 2 miles.
Location:
  • Town of Burlington
  • City of Woburn
  • Resident Engineer: Michael Pavao
    Construction Contract Value: $12,710,477.00
    Construction Bid Price: $10,994,383.48
    Initial Construction Estimate: $12,287,406.89
    District: District 4

    Contracts (3) Progress
    # 51304 -- Design -- Hwy Eng Open End
    Statewide - work will consist of providing engineering design and review services to the MassHighway on an open end basis for various statewide highway and bridge projects. Final
    # 64309 -- Design -- Hwy Eng Open End
    Work will consist of providing engineering design and review services to MassDOT on a task order basis for various statewide highway and bridge projects. Final
    # 69936 -- Construction Contract
    Resurfacing and Related Work on a Section of Interstate 95. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 11/04/2011
    Contract Information
    Project Designer: Consultant
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/30/2009
    Project Initiation Form PIF Entered 02/06/2009
    Project Initiation Form PRC Submitted 02/06/2009
    Project Review Committee PRC Approved 02/12/2009
    Project Review Committee Letter 02/19/2009
    Project Status Advertised 07/16/2011
    Project Status Advertised 07/30/2011
    Project Management
    100% Design 100% Package Received 06/13/2011
    75% Design 75% Package Received 10/20/2010
    75% Design 75% Package Comments to DE 03/04/2011
    Final Design PS&E Received 07/12/2011
    Final Design PS&E to FAPRO 07/20/2011
    Consultant Contract Process Scope to DE 05/22/2009
    Consultant Contract Process NTP Issued 06/24/2009