CANTON- NORWOOD- SHARON- WALPOLE- INTERSTATE MAINTENANCE & RELATED WORK ON I-95
Resurfacing and related work on I-95 in the Towns of Canton, Norwood, Walpole, Sharon, and Norwood between MM 20.7 and MM 23.6 for a total project length of 2.90 miles.
Location:
  • Town of Canton
  • Town of Norwood
  • Town of Sharon
  • Town of Walpole
  • Resident Engineer: Brian Lewis
    Construction Contract Value: $10,417,976.70
    Construction Bid Price: $8,782,642.10
    Initial Construction Estimate: $9,227,466.50
    District: District 5

    Contracts (1) Progress
    # 70375 -- Construction Contract
    Resurfacing and Related Work on a Section of Interstate 95. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 12/02/2011
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Interstate Maintenance
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 01/30/2009
    Project Need Form PNF Approved 02/06/2009
    Project Initiation Form PIF Entered 02/09/2009
    Project Initiation Form PRC Submitted 02/09/2009
    Project Review Committee PRC Approved 10/19/2010
    Project Review Committee Letter 02/19/2009
    Project Status Advertised 08/06/2011
    Project Management
    100% Design 100% Package Received 07/21/2011
    75% Design 75% Package Received 02/16/2011
    75% Design 75% Package Comments to DE 04/12/2011
    Final Design PS&E Received 07/26/2011
    Final Design PS&E to FAPRO 08/02/2011