CANTON- RANDOLPH- RESURFACING & RELATED WORK ON ROUTE 24
The project will resurface Route 24 in Randolph from milemarker 39 just north of the Canton/Randolph town line and milemarker 41 at the I-93 Route 24 interchange.
Location:
  • Town of Canton
  • Town of Randolph
  • Resident Engineer: Kevin Fuller
    Construction Contract Value: $5,816,283.00
    Construction Bid Price: $4,878,041.35
    Initial Construction Estimate: $4,976,009.10
    District: District 6

    Contracts (1) Progress
    # 72311 -- Construction Contract
    Resurfacing and Related Work on a Section of Route 24. Completed

    Bridges

    Contract Dates
    Notice to Proceed: 06/13/2012
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/04/2009
    Project Initiation Form PIF Entered 02/06/2009
    Project Initiation Form PRC Submitted 02/06/2009
    Project Review Committee PRC Approved 02/12/2009
    Project Review Committee Letter 02/20/2009
    Project Status Advertised 12/31/2011
    Project Management
    100% Design 100% Package Received 10/26/2011
    100% Design 100% Package Received 12/19/2011
    100% Design 100% Package Comments to DE 12/13/2011
    25% Design 25% Package Received 06/05/2009
    25% Design 25% Package Comments to DE 06/18/2009
    25% Design 25% Package Approved 06/26/2009
    75% Design 75% Package Received 10/29/2009
    75% Design 75% Package Comments to DE 12/04/2009
    75% Design 75% Plans Complete 11/23/2009
    Final Design PS&E Received 12/19/2011
    Final Design PS&E to FAPRO 12/28/2011