Project Description:
NORTHBOROUGH- RESURFACING & RELATED WORK ON ROUTE 20, FROM 20 FEET NORTH OF TOMBLIN HILL ROAD TO THE MARLBOROUGH TOWN LINE.
Resurfacing and related work on a section of Route 20 from MM 121.6 to 126.2 for a total project length of 4.6 miles.
Location:
  • Town of Northborough
  • Resident Engineer: Michael Sholock
    Construction Contract Value: $3,807,621.98
    Construction Bid Price: $2,790,417.30
    Initial Construction Estimate: $3,059,604.75
    District: District 3

    Contracts (1) Progress
    # 80491 -- Construction Contract
    Resurfacing and Related Work along a Section of Route 20 (Southwest Cutoff, Main and West Main Streets). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 05/23/2014
    Contract Information
    Project Designer:
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/06/2009
    Project Initiation Form PIF Entered 02/17/2009
    Project Initiation Form PRC Submitted 02/17/2009
    Project Review Committee PRC Approved 02/12/2009
    Project Review Committee Letter 02/20/2009
    Project Status Advertised 11/09/2013
    Project Management
    100% Design 100% Package Received 10/07/2013
    100% Design 100% Package Comments to DE 10/16/2013
    25% Design 25% Package Received 04/12/2013
    25% Design 25% Package Comments to DE 05/31/2013
    75% Design 75% Package Received 04/12/2013
    75% Design 75% Package Comments to DE 05/31/2013
    Final Design PS&E Received 10/07/2013
    Final Design PS&E to FAPRO 10/25/2013