Enter a City or Road name to search for a new project:
Advanced Project Search
Project Description:
BECKET- RESURFACING & RELATED WORK ON ROUTE 20, FROM MM 25.73 TO MM 30.94
Proposed work consists of micro-milling the roadway to an average depth of 2", sealing the milled surface with 1/2" of asphalt chip seal, and resurfacing the roadway with 1-1/2" of hot mix asphalt. The following items may also be included at select locations, as needed: milling and resurfacing side road approaches, full depth roadway repairs, repaving driveway aprons, adjusting granite curb, limited drainage structure repairs, reconstructing sidewalks for ADA compliance, replacing bit. conc. berm, placing dense graded crushed stone for shoulders, upgrading highway guard rail to current standards, placing new pavement markings and installing raised pavement markers.
Location:
  • Town of Becket
  • Resident Engineer: Darin Aitken
    Construction Contract Value: $2,862,423.00
    Construction Bid Price: $2,468,285.00
    Initial Construction Estimate: $2,959,081.00
    District: District 1

    Contracts (1) Progress
    # 75720 -- Construction Contract
    Resurfacing and Related Work along a Section of Route 8/20 (Chester & Jacobs Ladder Roads). Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 03/26/2013
    Contract Information
    Project Designer: In-House Boston
    Funding Source: Surface Trans. Program
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/09/2009
    Project Initiation Form PIF Entered 02/09/2009
    Project Initiation Form PRC Submitted 02/09/2009
    Project Review Committee PRC Approved 02/12/2009
    Project Review Committee Letter 09/10/2009
    Project Status Advertised 09/22/2012
    Project Management
    100% Design 100% Package Received 02/16/2010
    75% Design 75% Package Received 06/30/2009
    75% Design 75% Package Comments to DE 07/14/2009
    Final Design PS&E Received 04/09/2010
    Final Design PS&E to FAPRO 09/11/2012