Project Description:
FALMOUTH- RESURFACING & RELATED WORK ON ROUTE 28
The purpose of this project is to resurface Route 28 from milemarker 50.7 to milemarker 56.5 for a total project length of 5.80 miles.
Location:
  • Town of Falmouth
  • Resident Engineer: Richard McKenzie
    Construction Contract Value: $5,415,565.00
    Construction Bid Price: $4,359,409.80
    Initial Construction Estimate: $4,376,905.00
    District: District 5

    Contracts (1) Progress
    # 70962 -- Construction Contract
    Resurfacing and Related Work on a Section of Route 28. Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 01/27/2012
    Contract Information
    Project Designer: In-House Boston
    Funding Source: NATIONAL HIGHWAY SYSTEM
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/11/2009
    Project Initiation Form PIF Entered 03/03/2009
    Project Initiation Form PRC Submitted 03/03/2009
    Project Review Committee PRC Approved 02/12/2009
    Project Review Committee Letter 02/20/2009
    Project Status Advertised 09/10/2011
    Project Management
    100% Design 100% Package Received 08/17/2011
    75% Design 75% Package Received 05/27/2011
    75% Design 75% Package Comments to DE 08/04/2011
    Final Design PS&E Received 09/01/2011
    Final Design PS&E to FAPRO 09/06/2011