Project Description:
BOSTON- INTERSECTION & SIGNAL IMPROVEMENTS ON DORCHESTER AVENUE (15 LOCATIONS)
This project will make safety and mobility improvements at four major intersections along the Dorchester Avenue corridor; Andrews Square, Glover's Corner, Fields Corner and Peabody Square. Improvements at the remaining 11 signalized intersections along the corridor will consist of traffic signal equipment upgrades, interconnection and hardwire control to the Boston Traffic Management Center. Accessibility and bike accommodation improvements will also be included.
Location:
  • City of Boston
  • Resident Engineer: George Kavalaris
    Construction Contract Value: $14,919,115.00
    Construction Bid Price: $12,933,770.00
    Initial Construction Estimate: $13,611,680.00
    District: District 4

    Contracts (1) Progress
    # 60208 -- Construction Contract
    Intersection and Signal Improvements along Dorchester Avenue at 15 Locations. (ARRA Project) Completed

    Bridges

  • - none -
  • Contract Dates
    Notice to Proceed: 11/17/2009
    Contract Information
    Project Designer: Municipality
    Funding Source: American Recovery & Reinvestment Act
    See the Milestone Details tab for additional Project information
    Property Impacts - Right of Way
    no comments
    Environmental Impacts
    no comments
    Project Design
    no comments
    Project Funding
    no comments
    Public Involvement
    no comments
    Construction
    no comments
    Accelerated Bridge Program
    no comments
    No TIP Data Available For This Project
    Project Task Information
    Project Status
    Project Need Form PNF Entered 02/23/2009
    Project Initiation Form PIF Entered 02/25/2009
    Project Initiation Form PRC Submitted 03/03/2009
    Project Review Committee PRC Approved 05/14/2009
    Project Review Committee Letter 06/08/2009
    Project Status Advertised 08/22/2009
    Project Management
    100% Design 100% Package Received 06/08/2009
    100% Design 100% Package Received 07/02/2009
    100% Design 100% Package Comments to DE 06/15/2009
    100% Design 100% Package Comments to DE 06/23/2009
    100% Design 100% Package Comments to DE 06/26/2009
    25% Design Design Public Hearing 05/19/2009
    75% Design 75% Package Received 03/06/2009
    75% Design 75% Package Comments to DE 04/16/2009
    Final Design PS&E Received 07/23/2009
    Final Design PS&E to FAPRO 08/06/2009